Dashboard

Riverside Commerce Center · Hudson, WI
LIVE · Riverside
Project state is updating as the day unfolds
Owner Update
Hudson, WI
67%
Active Project

Riverside Commerce Center

Value
$4.2M
Start
Jan 06, 2025
Substantial Completion
Jul 18, 2025
8
Open RFIs
3
Overdue Submittals
14
Open Punch Items
41
Days to Completion
AI Insight
Today

3 submittals are overdue and sitting on the critical path. Electrical RFI 14 has been unanswered for 9 days and recommend follow-up today before it impacts the MEP rough-in milestone.

Today · Live
LIVE · Riverside
7-Day Lookahead
Mon
Slab pour, level 2 west bay
Tue
MEP rough-in coordination walk
Wed
Curtainwall delivery
Thu
Owner walkthrough, level 1
Fri
Roof membrane inspection
Sat
Site cleanup and material restock
Sun
No work scheduled
Project Leads
DK
Dana Kowalski
Project Manager
MW
Marcus Webb
Superintendent