Owner Project Update
Riverside Commerce Center
Hudson, WI · Week of September 9, 2026
Overall Progress
52%
41 days to completion
Open RFIs
9
Open Punch
14
Contract Value
$4.2M
This week's wins
- Foundation concrete complete across all sequences.
- Structural steel erection 95% complete, on track to finish next week.
- Concrete pour at level 2 west bay completed Monday with no mix issues.
- Curtainwall submittal markups returned, anchor depth clarification accepted.
At-risk items
Structural Steel Erection
+2d behind
Crane downtime on May 6 (1d) + RFI 08 slab edge clarification (1d).
Metal Deck and Slab
+1d behind
Downstream of steel erection delay.
Roofing System
+6d behind
TPO membrane submittal #004 sent back Revise and Resubmit. Inspection window slipping into critical path.
Decisions needed from ownership
- Submittal #004 Roofing Membrane System — owner to acknowledge revised turnaround commitment.
- Submittal #007 Mechanical Equipment Submittals — owner to acknowledge revised turnaround commitment.
- RFI #11 Curtainwall anchor depth — owner to escalate to EOR Structural.
Site progress